SR 520 Bridge Program: Medina to SR 202 Eastside Project What's happening now

We want to hear from you

Construction hotline:
425-998-5200

Email
Dan Galvin, dan.galvin@gcinc.com

E-mail updates:
Sign up for SR 520 Construction Updates

Regional construction information: 
King County Construction Update Web page
Floating bridge project construction information

Updated:  Monday, May 21
Please visit this page throughout the week, as we continually update it with the latest construction schedule information.

Check out our May 2012 SR 520 Eastside construction activities map (pdf 2 MB)

Lane and ramp closures
Nighttime construction noise
Changes to SR 520 west of 92nd Avenue Northeast

Tree removal and wall construction begins May 7 at Northeast Points Drive (pdf 2 MB)
Evergreen Point Road traffic shift (pdf 818 kb)
Wall construction begins around 92nd Avenue Northeast (pdf 4 MB)

Check out our construction progress

Contact us 


Live streaming construction cameras 




Click on the callout boxes on the map to watch the construction progress on the SR 520 Eastside Transit and HOV Project. A plugin may need to be installed to view streaming video.

SR 520 closures

  • Tuesday, May 22 to the morning of Wednesday, May 23 - Crews will completely close eastbound SR 520 floating bridge and highway from Montlake Boulevard to 92nd Avenue Northeast from 11 p.m. to 5 a.m.
  • Wednesday, May 23 to the morning of Thursday, May 24 - Crews will completely close eastbound SR 520 floating bridge and highway from Montlake Boulevard to 92nd Avenue Northeast from 11 p.m. to 5 a.m.
  • Wednesday, May 30 to the morning of Thursday, May 31 - Crews will completely close westbound SR 520 floating bridge and highway from 92nd Avenue Northeast to Montlake Boulevard from 11 p.m. to 5 a.m.

Lane and ramp closures

  • Monday, May. 21 to the morning of Tuesday, May 22 - Crews will close the right lane of eastbound SR 520 from Evergreen Point Road to 84th Avenue Northeast, from 11 p.m. to 5 a.m. for lighting and deck work.
  • Monday, May 21 to the morning of Friday, May 25 - Crews will close the 84th Avenue Northeast on-ramp to westbound SR 520, nightly from 9 p.m. to 5 a.m. for lighting and deck work.
  • Monday, May 21 to the morning of Friday, May 25 - Crews will close the right lane of westbound SR 520 from 84th Avenue Northeast to to Evergreen Point Road, nightly from 9 p.m. to 5 a.m. for lighting and deck work.
  • DRIVER ALERT - Tuesday, May 22 to the morning of Thursday, May 24 - Crews will close eastbound SR 520 from Montlake Boulevard to 92nd Avenue Northeast, nightly from 11 p.m. to 5 a.m.
  • Thursday, May 24 to the morning of Friday, May 25 - Crews will close the right lane of eastbound SR 520 from Evergreen Point Road to 84th Avenue Northeast, from 11 p.m. to 5 a.m. for utility, lighting and deck work.
  • DRIVER ALERT - Wednesday, May 30 to the morning of Thursday, May 31 - Crews will close westbound SR 520 from 92nd Avenue Northeast to Montlake Boulevard from 11 p.m. to 5 a.m.

Construction Update page for construction information around the region.

Expect some nighttime construction noise

During the week of May 14 night work is scheduled at the following locations:

  • Monday, May 21 to the morning of Friday, May 25 - Crews will build bridge decks, strip forms from diaphragms, and install utilities at 84th Avenue Northeast.
  • Monday, May 21 to the morning of Friday, May 25 - Crews will be patch concrete and install under-deck lighing at Evergreen Point Road.

Changes to SR 520 west of 92nd Avenue Northeast

Effective April 30, we are closing the westbound bus-only lane between 92nd Avenue Northeast and Evergreen Point Road flyer stops. This change will be in effect until the new median transit stops and HOV lanes are opened, by December 2013.

Closing the bus-only lane in this location allows vehicles entering SR 520 at 84th Avenue Northeast to accelerate and merge more effectively. Tolling on the SR 520 floating bridge has resulted in reduced volumes in the general purpose lanes, and traffic analysis shows that moving buses into the general purpose lanes will not adversely affect bus or general purpose travel times during project construction.

We're making this change because we widened a median work zone near 84th Avenue Northeast to construct a pier wall for new overpass at that location—a change that leaves less space for mainline vehicles and vehicles entering SR 520 from the 84th Avenue Northeast on-ramp.

Westbound buses, carpools, vanpools and motorcycles are required to merge into the general purpose lanes east of the new median work zone to make room for drivers entering the highway at the 84th Avenue Northeast on-ramp.

Changes to Bellevue Way Northeast

Drivers that use Bellevue Way Northeast near SR 520 should anticipate a few changes to the interchange.  Check our Bellevue Way Northeast fact sheet (pdf 630 kb) for more details.

Points Loop Trail detour

The Points Loop Trail is closed between Evergreen Point Road and 92nd Avenue Northeast for up to two years while crews construct project improvements. Bicyclists and pedestrians will be detoured to Northeast 28th Street and Northeast Points Drive. 


We want to hear from you

Construction hotline :
425-998-5200

Email
Dan Galvin, dan.galvin@gcinc.com

E-mail updates:
Sign up for SR 520 Construction Updates

Regional construction information:
King County Construction Update Web page



Evergreen Point Road camera92nd Avenue Northeast camera84th  Avenue Northeast construction cameraBellevue Way Northeast camera108th Northeast construction cameraEvergreen Point Road camera92nd Avenue Northeast cameraBellevue Way Northeast camera84th Avenue Northeast camera108th Avenue Northeast camera